Eastern Creek Warehousing
Client
Taylor Construction Group
Value
2.5 Million
Location
Eastern Creek, NSW
Status
Completed
The Eastern Creek Warehouse project consists of bulk earthworks, stormwater, detail excavation and various pavement works.
On completion, the project will include earthworks steming across a 55,000m2 lot, including over 13,000m3 level 1 supervised cut to fill, 700m of divergent drains, and importation of over 15,000T of sandstone into the job for a 12,500m2 building pad.
Scope of Work:
- Clear site from all weeds and grubs – 55,000m2 site.
- Bulk Earthworks – Cut to fill 13,000m3 and stockpile on site.
- Construct building pad with sandstone – 12,000m2.
- Pavement Preparation
- Detail Excavation
- Stormwater and Drainage